St Peters Street—Aberdeen
Wednesday, March 26th, 2014
The initial piling of the ground has been carried out on the footprint of the proposed new student accommodation flats within the City. Skene Group Ltd have now commenced with the foundations, installing the reinforced tied re bar to form the ring beams, installing beam form and pouring the concrete to same. Skene Group Ltd are installing the 900mm dia precast concrete attenuation pipework and the new sewer line to service the development now.