A further extension on the back of a new shed by one of the Skene Group Ltd clients resulted in a large area being pumped in one day. The new factory shed was protected by polythene prior to the pour. The area was designed so that the surface water would fall away from the new building and out of the weepers of the retaining wall. Skene Group Ltd serviced the works package from its outlets in Glenrothes Fife, running in type one fill from the quarry and concrete from the now very busy Glenrothes plant. The job was difficult to service as the new yard was within a raised area, resulting in challenging solutions to preserve the retaining walls whilst filling and consolidating.